What is an RFI in construction?
Rev. November 24, 2026Short answer. An RFI (request for information) is a formal written question from the contractor to the design team or owner when the drawings, specifications or contract do not say clearly what to build. Its answer becomes part of the project record and can lead to a change order if it changes cost or time.
Who sends an RFI, and to whom?
The general contractor usually sends RFIs to the architect, who answers or routes them to the right engineer. Subcontractors raise most questions, but they send them through the GC so there is one numbered log. Owners get RFIs when the question is about scope, budget or a decision only they can make.
When should a GC send an RFI?
When the documents conflict, leave something out or cannot be built as drawn, and the answer affects what gets built. Do not use an RFI to ask for a change you want, to confirm something the drawings already show, or to put a dispute on record; those slow the design team down and get answered slowly.
Is an RFI a change order?
No. An RFI asks a question. If the answer adds cost or time, the contractor opens a change event or a potential change order and points to the RFI as the reason. Keeping the two linked is what makes the cost traceable later.
Is there a standard RFI form?
Many teams use their software’s form. AIA publishes G716, Request for Information, as a standard paper form. Whatever the form, it needs the same core fields: number, subject, question, references, suggested answer, impacts, ball in court and dates.
Comparing tools? See which RFI software fits a GC, and what the RFI plan costs →
Asked often
- What does RFI stand for in construction?
- Request for information: a written question about the drawings, specifications or contract, sent to the design team or owner.
- How long does an architect have to answer an RFI?
- Whatever the contract says. Many contracts set 5 to 10 working days; check the general conditions and Division 01 of your specifications.
- Can an RFI change the contract price?
- Not on its own. An RFI answer that changes the work leads to a change order, which is what changes the price or time.