Rev. November 24, 2026 · CSV, opens in Excel or Google SheetsShort answer. An RFI log needs 14 columns, from the RFI number and question to ball in court, due date, cost and schedule impact, and what the answer changed. Download the RFI log template (.csv).
The columns, and what goes in each
| Column | What goes in it |
|---|---|
| 01 RFI number | Sequential, never reused: RFI-001, RFI-002. Some teams prefix by discipline. |
| 02 Subject | Eight words or fewer, specific enough to find later: "Level 3 beam pocket depth at grid C". |
| 03 Question | One question per RFI, stated so it can be answered yes, no or with a dimension. |
| 04 Drawing and spec reference | Sheet, detail and spec section the question is about. |
| 05 Suggested answer | What the contractor proposes. Architects answer faster when there is something to accept. |
| 06 Cost impact | Yes, no or unknown, so a change event can follow. |
| 07 Schedule impact | Yes, no or unknown, with the activity it holds up. |
| 08 Ball in court | Who has to act next: architect, engineer, owner, subcontractor or GC. |
| 09 Date sent | When it left the GC. |
| 10 Due date | From the contract’s response time, often 5 to 10 working days; check yours. |
| 11 Answer | The response as given, with who gave it. |
| 12 Date answered | When the answer came back. |
| 13 Status | Draft, open, answered, closed. |
| 14 Linked records | Change events, submittals or drawing revisions the answer caused. |
When does a spreadsheet stop working?
When more than one person edits the log, when RFIs need reminders as they near their due date, when the answer has to reach the field and the drawing set, and when answered RFIs need to turn into change events. That is the point where RFI software pays for itself.
Asked often
- What columns should an RFI log have?
- At minimum: rfi number, subject, question, drawing and spec reference, suggested answer, cost impact, schedule impact, ball in court, date sent, due date, then the answer, date answered, status and linked records.
- Is a spreadsheet good enough for an RFI log?
- For a small project with one PM, often yes. It breaks down when several people edit it, when you need ball in court reminders, or when answers have to reach the field and the drawings automatically.